|
Advertising supplement provided by
American Institute of Steel Construction
By Larry Flynn
Steel Industry: A Model for Success
While most architects and other members of the building team
are only beginning to apply BIM to projects, the structural
steel industry is using 3-D modeling and interoperabilitythe
use of software systems that are able to communicate and exchange
data and information through a neutral file formatto
integrate the design and construction process and speed the
delivery of the structural steel package. Structural engineers
are collaborating with steel detailers, fabricators, and erectors
to share and exchange 3-D model information to create detailed
designs for steel-framed buildings with tight tolerances.
On numerous projects, this allowed mill orders to be placed
earlier and steel to be delivered and erected on site more
quickly, with few, if any field changes required. Fewer field
changes enable the steel teams to provide a quality product,
with less waste, and greater safety.

T3-D modeling and
team integration enabled steel erection of
the Denver Art Museum expansion to be completed
two months ahead of schedule.
Photo credit: Structural Consultants Inc.
Design
Architect: Studio Daniel Libeskind |

The 3-D visualization model used on the Denver
Art Museum expansion by local architect Davis
Partnership, Studio Daniel Libeskinds
joint venture design partner, became a BIM
model during the project.
Photo credit: Miller Hare |
|
|
Using BIM on General Motors new $300million V6
engine plant in Flint, Mich., enabled the steel mill order
to be placed eight weeks earlier than typically would be possible
and steel erection began eight days early, says Lawrence F.
Kruth, P.E., engineering and safety manager for Douglas Steel
Fabricating Corp., Lansing, Mich. Construction of the plant
was completed five weeks ahead of schedule with no change
orders, says Samir Emdanat, manager of advanced technologies
for the architectural/engineering firm Ghafari Associates,
Dearborn, Mich. BIM enabled the projects integrated
building team to shave 24 weeks off what typically would have
been an 85-week design and construction schedule. In benchmarking
previous projects, GM estimates that three to five percent
of total construction costs would have been saved by implementing
BIM on those projects, according to Laird Landis, GMs
senior technological engineer.
Modeling the steel and mechanical, electrical, and plumbing
(MEP) with tight tolerances meant that the steel frame, sheet
metal, and piping all fit into place in the field like an
erector set, reducing construction waste. Less waste and field
work resulted in a safer construction site, with only one
injury recorded on the project, which was unrelated to construction
activity.
In Denver, the need to understand, document, and coordinate
the complex design by Studio Daniel Libeskind for the Denver
Art Museum expansion, scheduled to open in Fall 2006, dictated
sharing of the 3-D model between Denver architect Davis Partnership
and the projects structural engineer, steel connection
designer, and steel delivery team. Its difficult
to believe the project could have been done without BIM,
says Davis Partnerships Maria Cole, AIA. Working with
general contractor M.A. Mortenson, the integrated design-build
steel team completed the projects steel erection two
months ahead of schedule, after starting the design process
two months behind schedule and returning $400,000 to the owner
in the process.
|