|
Case Study
Historic Pontiac Mills, Warwick, Rhode
Island. Estimated date of completion: not available
The firm of DAgostino Izzo Quirk Architects (DAIQ),
based in Somerville, Massachusetts, has taken a prominent
role in addressing brownfield conditions at Historic
Pontiac Mills, in Warwick, Rhode Island. The 350,000-square-foot
site along the Pawtuxet River was home to the original
Fruit of the Loom textile mill, dating back to the mid-1800s.
Production stopped in the 1970s.
In 1986, a landfill east of the property was designated
by EPA as a potential hazardous-waste site; a tiny portion
of this landfill extended onto the Pontiac Mills site.
In addition, fuel oil, arsenic, beryllium, and lead
were found in other locations. The property owners at
the time wanted to sell, but no lender would touch such
a site unless it also received brownfield designation.
 |
|
Historic Pontiac Mills (above),
once home to Fruit of the Loom, is to be converted
into multipurpose spaces.
Photography: © Richard
Marthers
|
In 1996, DAIQ began helping a developer interested
in the property. Neither had prior experience with brownfields.
But we had experience with other types of consultants,
says project architect John Giangregorio, a principal
at DAIQ. The architecture firm found an environmental
engineer with whom they felt comfortable, and so began
the complex process.
Although the first developer never exercised his option
to buy, nor did a second developer for whom DAIQ
also worked, the firm gradually became attached to the
site. Explains Giangregorio, We had been developing
good relationships with the town while shepherding the
various master plans through the city development process.
So when the third developer put an option on the property,
they too hired DAIQ and the team of technical
consultants that they had cultivated over the years.
This third developer, Hampton Hodges, bought the property
in January 2003, soon after the brownfields settlement
agreement was reached.
The architecture firm managed the whole project. Environmental
engineers take a narrower focus: If they can satisfy
the states department of environment, their job
is done. The environmental engineer worked directly
for the developer, so the architect had no liability
for that part of the work. The civil engineer and landscape
architect worked under the architect. All four professionalswith
their varying expertiselooked at options together.
The most recent master plan calls for the conversion
of existing structures into office, hotel, and retail
spaces. New construction will include a portion of the
hotel complex and a three-story office building. The
project will be implemented in three phases, progressing
from the west side, which requires minimal environmental
remediation, to the more complicated cleanup on the
east. In this way, the owner will begin to generate
income from the development in one phase to undertake
the more costly remediation in the next.
The design team negotiated with the Rhode Island Department
of Development to cap the landfill portion of the sitewhich,
as it turned out, only contained relatively nonhazardous
automobile fluff and textile remnantsrather than
excavate and remove it, and to build the parking in
phases. Two layers of asphalt matching the footprint
of the planned garage will be applied as an impermeable
cap over the northern portion of the landfill in the
first phase of construction. The southern portion will
be covered by an impermeable membrane sheet and 18 inches
of soil supporting low-growing vegetation. Piles, which
will minimize disturbance of the contaminants and extend
deep enough below the landfill to more stable ground,
will be driven for the garages foundation at the
beginning of the second phase.
Giangregorios advice: Know the process.
Some can be learned by having a good relationship with
the regulatory agencies. And find an environmental engineer
whom you can trust. N.B.S.
|