|
Additional
Reading
Page 11 of 11
          
By: Robert Grupe
Director, Architectural and Technical Solutions, United States
Gypsum Company
Phil Shaeffer
Manager, Codes and Technical Support, United States Gypsum
Company
Dean Updegrove
Product Marketing Manager, United States Gypsum Company
Section 2
HORIZONTAL GYPSUM SHAFT WALL APPLICATIONS
In recent years, vertical gypsum shaft wall applications
have been turned on their sides and are now being used for
a whole series of new, but equally critical, applications.
When applied horizontally, gypsum shaft walls serve as thin,
fire-resistant assemblies that are ideal for use under ducts,
on stair soffits or for corridor ceilings that require fire
protection.
A key to these applications lies in the C-H-stud, which
enables application from one side only. Stud depth and gauge
are determined by stud span, which is calculated by using
the manufacturer's limiting spans table (not to be confused
with a limiting heights table used for vertical shaft wall
applications).
| Limiting Spans -
Horizontal Shaft Walls (1) |
| Stud Style |
Single-layer 5/8-inch gypsum panels (2) |
Double-layer 1/2-inch gypsum panels (2) |
Triple-layer 1/2-inch gypsum panels (3) |
| 212CH25 |
6'-7" |
6'-0" |
6'-5" |
| 212CH22 |
9'-4" |
8'-6" |
7'-11" |
| 212CH20 |
10'-3" |
9'-2" |
8'-3" |
| 400CH25 |
8'-8" |
7'-10" |
8'-6" |
| 400CH20 |
14'-6" |
13'-2" |
12'-0" |
| 600CH20 |
17'-5" |
15'-10" |
13'-8" |
| (1) Based on L/240 allowable deflection
and JR24 runner. (2) Allowable steel stress reduced 50
percent. (3) Full steel stress allowed based on ASTM E119. |
On the finished side of the system, over the 1-1/2 inch flange
of the C-H stud, one to three layers of fire-rated gypsum
board can be attached over the 1-1/2 inch flange of the C-H-stud.
The thickness of panels - either 1/2 inch or 5/8 inch - and
the number of layers determine the fire endurance rating of
the wall.
The System
When a gypsum shaft wall system is installed vertically,
the studs do not have to be screw-attached to the runner.
However, in the horizontal mode, pan-head screws are required
to transfer the loads from the system back to the structure.
This should be designed prior to the release of the contract
documents. The gypsum face panels are installed with a suitable
length bugle-head screw. The correct screw spacing is determined
by the corresponding fire test. Appropriate corner bead and
trim are used with a joint finishing system to complete the
installation. The proper location of any control joints should
be predetermined.
System Limitations
Horizontal gypsum shaft walls are intended to carry dead
load only. They are not designed to carry any live load. They
are not a floor-ceiling system. Manufacturers' limiting spans
tables only consider the dead load of the assembly, and the
weight of the gypsum panels and the various steel components.
They do not include any concentrated loads from fixtures that
might, (but should not) be supported by the C-H stud. The
shaft wall cannot be used for storage. Further, manufacturers'
limiting span information does not factor in the added load
of a mechanic installing the system.
System Application
The fire endurance testing procedures for horizontal gypsum
shaft walls are specifically detailed per ASTM E119. By definition
these assemblies are called either floor/ceiling or roof/ceiling
systems. As the definition implies, a floor/ceiling system
must have the ability to carry all the live and dead loads
it was designed for. Stair soffits, corridor ceilings, and
horizontal metal duct enclosures only serve to provide fire
separation, and are not intended to carry any live loads.
The Council of American Building Officials (CABO) National
Evaluation Service Report Number 258 covers gypsum shaft wall
systems in general, and horizontal applications specifically.
Per this model code document, if the intended application
is specific to stair soffit or corridor ceiling, a single-layer
(1-hour) or double-layer (2-hour) system is appropriate. All
other installations require a triple-layer, fire-tested system.
| Horizontal Gypsum
Shaft Wall System Selector |
| System |
1-hour Stair Soffit/ Corridor Ceiling |
2-hour Stair Soffit/ Corridor Ceiling |
2-hour Horizontal Membrane |
| 2-1/2 inch, 25 gauge C-H-stud; 2-1/2 inch J-Runner;
1 inch gypsum shaft liner panel; single layer 5/8"
Type C core gypsum panel |
X
|
|
|
| 2-1/2 inch 25 gauge C-H-stud; 2-1/2" J-runner;
1 inch gypsum shaft liner panel; double layer 1/2"
Type C core gypsum panel |
|
X
|
|
| 2-1/2 inch, 25 gauge C-H-stud; 2-1/2 inch J-runner,
1 inch gypsum shaft liner panel; triple layer Type C core
gypsum panel |
|
X
|
X
|
|
Note: Stud and runner size and gauge are minimums,
use span table to determine proper size.
|
Page 11 of 11
          
|