|
Client, architect, and Construction
manager must perform a delicate balancing act to shrink the
construction process and save time and money.
By Barbara Knecht
Risky business
Fast-track construction is not suitable for the risk-averse
owner, architect, or construction manager. No construction
project is immune to delays, but all of the advantages can
evaporate and the disadvantages multiply if the process is
not closely managed to anticipate the unexpected and resolve
problems instantly.
 |
NBBJ pushed the limits
of 3D modeling (left and below) to reduce the delivery
time by 50 percent. The architects created the design
with Alias/Wavelength software running on high-end
Silicon Graphics (SGI) workstations. (See Digital
Architect) |
Reebok International World Headquarters
Canton, Mass.
Architect: NBBJ, Seattle
(Scott Wyatt, partner in charge; Richard G. Buckley,
partner in charge, competition; Steven McConnell,
design principal)
Date of completion: June 2000
Construction manager: Turner/OConnor |
 |
|
Project management is the key to success. No matter which
principal participant (architect, construction manager, or
owner) is driving a particular set of decisions, the other
two will have to be flexible and willing to compromise as
each gives input at every stage of design and construction.
Having the construction manager on board early will always
yield a better product. In fast track, many other design decisions
may be controlled by schedule and directed by the construction
manager, including material choices and construction methods.
A construction manager who knows the market conditions at
the time of construction may recommend against a material
or a trade that is in short supply. In a fast-track project,
schedule rules decisions. For some, there is a positive aspect
to this parameter. Jim Wilson, president of Ewing Cole Cherry
Brott in Philadelphia explains, I like [fast tracking]
because it imposes discipline over the decision-making process.
Sometimes with no schedule, things just keep changing.
Most of the Ewing Cole Cherry Brotts projects are fast
tracked, from the Whitehall-Robins Pharmaceutical Research
and Development Facility in Richmond, Virginia, to the new
stadium for the Philadelphia Phillies. Whitehall-Robins included
demolition, renovation, and new construction on a 30-acre
site, all while operations continued uninterrupted.
When a site was selected at the close of 1999 for a new
stadium for the Phillies, the team owners specified a 2004
opening. By fast tracking the project, a 55-month process
was compressed to 39 months by a couple of means. The first
construction packagesexcavation and water removalwent
out for bid nine months after the project began. Piling drawings
were issued postdesign development, and subsequent packages
have been issued steadily as the building has risen out of
the ground. There hasnt been a lot of rethinking
of the main concepts; the major needs were met in the schematic
phase. But we began to refer to it as a renovation project,
as changes were made in meetings with the Phillies after the
piling drawings were out to bid, remarks Bob McConnell,
the project architect.
|