BIM Lawsuit Offers Cautionary Tale

May 19, 2011

Insurance settlement related to a building information model shows that BIM without communication can be costly.

[ Page 3 of 3 ]

By Nadine M. Post in Pittsburgh
This article originally appreared in Engineering News-Record

“Even greater opportunities exist for increases in productivity as more designers allow fabricators greater access to models, models start being reviewed as opposed to detailed drawings, and fabricators open their dimensionally accurate models to other trades and specialties,” said Moor.

Rate this project:
Based on what you have seen and read about this project, how would you grade it? Use the stars below to indicate your assessment, five stars being the highest rating.
----- Advertising -----

To facilitate engineer-fabricator model interchange, engineers should model members to the top of steel on center lines, said Rob Schoen, founder of Axis Steel Detailing Inc., Orem, Utah. Columns should be continuous or break at correct splice elevations. Beams should be continuous or go to the correct work points.

Engineers responded that requests might take some extra effort but could be accommodated without any problems.

Technology is one reason 3D model approval is slow to launch. To facilitate the process, one steel fabricator, the Herrick Corp., has invested in a proprietary application-user interface that sits on top of Tekla Structures 3D modeling and detailing software.

Typically, a detailer extracts 2D drawings from the 3D model and sends the 2D drawings for approval. If the detailer must change the model, the 2D drawing must be either re-created or adjusted.

A rule of thumb is that the fabricator spends 60% of the time modeling and connecting the structure and 40% on extracting the drawings. Changing the model before the 2D drawings are extracted means extracting the drawings only once, says Wayne Morrison, preconstruction manager in Herrick's Stockton, Calif., office.

Herrick has approved models on three projects to date. To use its system, an engineer must have a Tekla engineering license. The engineer exports a file from its model to Herrick.

“We can see all the changes, make corrections and produce the 2D drawings once,” says Morrison. The system cuts approval turnaround time by at least 25%, he adds.

share: more »

[ Page 3 of 3 ]

 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.

----- Advertising -----
----- Advertising -----
McGraw-Hill Construction

Search Sweets

Example: Building Products, CAD, BIM, Catalogs
Search
Reader Feedback
Most Commented Most Recommended
Rankings reflect comments made in the past 14 days
Rankings reflect comments made in the past 14 days