|
By Nancy B. Solomon, AIA
Through a combination of grand stairs and public elevators,
the new circulation space navigates a 21-foot drop in elevation
between the historic street entrance at Mount Vernon Place
and the new door to the campus's interior plaza. A new one-story
addition between the original Conservatory building and the
renovated row of 19th-century structures provides an accessible
route, plus gallery space, from Washington Place to the arcade's
plaza entrance. Improved vertical circulation at the south
end of the arcade offers a more direct and appropriate passageway
for patrons parking below grade. This same route also provides
access to new practice spaces that were inserted underneath
the plaza, adjacent to the garage.
Inserting the arcade's relatively light structure into the
original buildings' massive brick walls was relatively easy,
but nonetheless required some technical maneuvering. Explains
project manager Carl Elefante, AIA, the Conservatory and Library
buildings had been built according to different structural
rhythms. "We built the arcade according to the library's
12-foot module because it was more regular, and because we
wanted to leave the Library's brick wall and stack-room fenestration
exposed." But, because of the Conservatory's own internal
load conditions, the corresponding locations on its exterior
brick wall were not necessarily well suited to handle any
additional vertical load. A new steel ledger beam, therefore,
had to be hung from the Conservatory wall to transfer loads
to more appropriate points. Architecturally this was not a
problem, as the designers planned to cover the Conservatory's
brick wall (whose original fenestration had been sealed years
ago to darken the interior performance space) with acoustical
insulation (to isolate the concert hall) and drywall. The
arcade's new steel trusses are fixed into beam pockets created
in the Library's brick wall and rest on slip joints on the
new ledger beam of the Conservatory wall, to accommodate thermal
expansion and contraction.
The excavation for the lower levels of the arcade and the
underground practice rooms, however, was more daring since
it involved significant underpinning of the original load-bearing
brick walls. Says Elefante, "By the time you hit the
foundation, the walls are four feet thick." The structural
engineer designed the underpinning and reviewed every submittal
very carefully to ensure that the contractor was proceeding
according to a very methodical process, building one pier
at a time. And extremely sensitive monitoring devices were
placed at the underpinning locations to keep close tabs on
how much the historic structure was settling due to the work.
More than anything else, the Conservatory desperately wanted
a well-designed rehearsal room for its orchestra. At the same
time, given the tight site and historic nature of the building,
this was the most difficult problem to solve. The Institute,
in consultation with Acoustic Dimensions of New Rochelle,
New York, was determined to convert East Hall-- the original
lecture room in the Library Building-into such a space before
Quinn Evans was retained. It was up to the architecture firm,
however, to make this a reality.
The hall was designed with tiered platform seating and a
speaker's dais. When the architects arrived, the space was
being used as a makeshift music classroom and library storage
space. Ten brick arches spanned visible brick pillars, which
clearly presented sightline challenges for the intended function.
On closer inspection, however, the architects discovered a
single, slender cast-iron column hidden within the storage
area. Archival research and limited destructive testing revealed
that the other pillars were indeed brick casings around the
same cast-iron element. It was a "yahoo" moment
for the architects, recalls Elefante, who were relieved to
know the removal of these bulky outer shells would be in keeping
with their preservation goals.
Alas, their structural work was not over. These very slender
cast-iron columns, which held up the six floors of stacks
above, were built in 1875. According to Elefante, structural
engineering guidelines were revised after that date to add
a necessary factor of safety. In addition, analysis of the
slenderness ratio for these columns indicated that, by today's
standards, they were too thin for their height. To resolve
these structural problems, steel pipes were run from the middle
of the columns to each other and to the exterior masonry wall.
For fire protection, the columns were completely encapsulated
with a cast plaster housing that echoes the cast-iron style.
The new horizontal bracing was finished with intumescent paint,
a special coating that, when exposed to heat, expands into
a fire-rated foam.
The renovated hall features "box-in-box construction"
so that the inner performance space remains acoustically separate
from the rest of the building by preventing sound energy from
passing between the inner structure of the hall and the outer
structure of the building. Drywall is installed on framing
suspended by spring isolation hangers from the slab above.
Framing for the double-height walls are supported by sway
braces, which are often used in seismic construction and consist
of two "u"-shaped interlocking forms separated by
a neoprene pad. And the floor slab is poured on a deck that
floats over hundreds of one-foot-on-center neoprene pucks.
|