|
In Berlin, meticulous sitework and
off-site production help piece together a sober memorial
By Deborah Snoonian, P.E.
 |
 |
 |

Each stele was lowered into place with a crane (top).
Formwork for the coffered ceiling (middle) followed the
sites lines, and the concrete was left uncoated
(above).
Courtesy Eisenman Architects |
The field of steles (pillars) at Eisenman
Architects Memorial to the Murdered Jews in Europe [page
120], and the rolling terrain and visitors center they sit
on, required close coordination of design and engineering
issues during construction.
The 2,711 reinforced, self-compacting
concrete steles were prefabricated off-site at an average
rate of about 60 per week, depending on their size (the shortest
are about 1.6 feet tall; the tallest are 15 feet). The design
team and the fabricator, Firma Geithner, checked each stele
against an approved prototype before authorizing it for shipment
to the site. Meanwhile, the 4.7-acre site was filled in and
graded to form the memorials gently undulating topography.
A grid plan for the steles was laid down, and the sites
soil was then excavated to create individual terraces
of compacted soil where the steles would sit.
Working with engineers Buro Happold,
the design team conceived what are essentially rectangular
strip foundations, or footings, to support the steles. Each
one is held up by two such footings. Four extra supporting
bumps fitted with rubber gaskets were added to
each footing to accommodate the varying weights and tilt angles
of the steles. Installation was completed in December 2004.
As the sitework and stele fabrication
progressed, the below-grade visitors center was taking shape.
Structurally, it consists of simple retaining walls and concrete
columns supporting a poured-in-place concrete coffered ceiling
that varies in height as it mimics the rolling topography
above. Wood forms were built for the ceiling pour, with wood
beams and ribs overlaid by large sheets of plywood to re-create
the land form. The construction team used MDF board to hollow
out spaces for the 1-foot-deep coffered areas. All the concrete
was left uncoated, which contributes to the centers
stark ambience.
|